N. Shallowford at N. Peachtree & Ellwyn Dr. Roundabout Project

Construction is scheduled to begin February 5th on the N. Shallowford at N. Peachtree & Ellwyn Dr. Roundabout. The project includes the conversion of the existing North Peachtree Road at North Shallowford Road intersection into a single lane compact roundabout. Additional work includes full depth pavement reconstruction, milling of existing asphalt, concrete vertical curb, concrete sidewalk, concrete driveways, new roadway signage and striping, storm drainage, landscaping, traffic control and more! Construction is expected to be complete on November 25, 2024. Follow us on social media and visit our website, www.chambleega.com, for project updates and road closures.

Construction Dates
  • Stage 1 
    • The change to the intersection control is a temporary condition to allow construction to begin for the conversion to a roundabout intersection. Stage 1 traffic shift will occur from approximately February 20th to June 1st 2024. Electronic signs will be placed on each approach 10 days prior to February 20th , to warn the general traffic of the intersection control change and when it will be implemented.2024 02 06_N Shallowfor N Peachtree Traffic Shift STAGE 1_Display - Copy
  • Stage 2
    • June 1st to June 28th 2024 (Traffic shift rendering will be provided by May 2024)
  • Stage 3
    • June 28th to September 2024 (Traffic shift rendering will be provided by May 2024)
  • Stage 4
    • September 2024 to November 1st 2024 (Traffic shift rendering will be provided by August 2024)
  • Approximate Completion Date
    • November 15th 2024